Conference Chairperson & Opening Remarks
Martin Cooney, Partner and Head of the Byrne Wallace Shields LLP Construction Law Team
How the Public Works Contract Allocates Risk from Day One
Speaker: Robert Rooney, Partner, Mason Hayes and Curran
- The contract structure and the documents that matter most when disputes emerge
- Order of precedence and the practical impact of clarifications and amendments
- Where assumptions made at tender stage create later arguments on scope, design, pricing and responsibility
- The recurring risk allocation problems that continue to shape claims and disputes
Tender Clarifications, Pricing Assumptions and the Problems They Cause Later
Speaker: Shane O'Connor, Partner, RDJ
- Post-tender clarifications and where they alter the commercial understanding of the job
- Qualifications, exclusions and assumptions that resurface during delivery
- Abnormally low or unrealistic pricing and how it feeds later claims behaviour
- What contracting authorities and tenderers need to watch for before the contract is signed
Design Responsibility Creep on Employer-Designed Contracts
Speaker: Paul Tohill, Legal Director, Browne Jacobson LLP
- Where responsibility is being pushed onto contractors despite employer-designed wording
- Temporary works, specialist design elements, offsite manufacture and coordination risk
- Drawings, specifications and performance requirements that shift liability by stealth
- The contract and document trail that matter when design responsibility becomes disputed
Clause 10.6 and the Real-World Valuation of Change
- How the valuation sequence operates in practice
- Similar work, similar conditions and where disagreements usually begin
- Fair valuation and the recurring arguments around rates, prelims, overheads and margin
- What happens when pricing documents do not provide a workable route to valuation
Clauses 10.3 and 10.7: Notices, Delay Costs and the €0 Rate Problem
Speaker: Conor Ahern, Solicitor,Ahern Law
- What must be done to preserve entitlement under the notice provisions
- The practical effect of blank, nominal or unrealistic delay rates
- When time is granted but recovery of cost becomes far more difficult
- The recurring disputes around delay costs, extended prelims and supporting records
Extensions of Time, Programme Contingency and Constructive Acceleration
- How programme contingency interacts with delay events and extension of time decisions
- What happens when contingency is exhausted, ignored or poorly understood
- Concurrent delay, sequencing issues and the practical difficulties in assessing entitlement
- Acceleration pressure where entitlement is disputed but progress must continue
The Employer’s Representative: Decisions, Determinations and Where Things Break Down
Speaker: Ciara Keegan, Barrister at Law, The Law Library
- The ER’s powers, duties and practical limits under the contract
- What a properly reasoned determination should look like
- Certification, communication failures and the impact of weak contract administration
- How poor ER decisions can drive avoidable claims and escalation
Payment, Named Specialists, Subcontractor Exposure and Escalation Strategy
Speaker : Chris Wheeler, Head of Construction, Dillon Eustace LLP
- Payment certification issues and the records needed to support entitlement
- Where named specialists and subcontractors are exposed when delay or change arises
- The limits of downstream protection under linked contract structures
- When issues should remain at project level and when escalation to Project Board or conciliation becomes the better course